Question 7
« on: April 20, 2009, 02:55:54 PM »
QUESTION 7
(a)  Trade waste must be cooled before discharging to a drain or sewer. In relation to this
statement answer the following questions.
 (i) A cooling tank must be a specific size. State the factor that determines this size.
 (ii) Draw a side elevation of a typical cooling pit. [Cooling tank in ground].
(4 marks)

(b)  A petrol trap is one type of special purpose interceptor trap. State what hazard the
interceptor trap prevents and how it prevents it.
 
 
 
 
(2 marks)
(c) State when a sewage pump is required on a foul water drainage system.
 
(1 mark)
(d)  State where the non-return valve on the outlet of a sewage pump system should be
installed in relation to the isolating valve.
 
(1 mark)
Total 8 marks

Linkback: https://www.plumbers.nz/drainlaying-exam-november-2007/25/question-7/231/

Offline Plumber

  • Administrator
  • Hero Member
  • *****
  • Posts: 736
  • Karma: +52/-2
  • ***#1 Plumber***
Re: Question 7
« Reply #1 on: April 27, 2009, 07:45:35 PM »
Question 7
1) The tank must be large enough to hold the hot water discharge until cooled below 50 deg. C, before it is displaced by incoming water.
2) check jpeg

b) The trap separates and holds any oil or petrol present in wastes before it discharges to the sewer. The trap works on the principle that oil and petrol, being lighter than water, will float on the surface when the flow is reduced.
Please note that the advice I am giving is only my opinion and not necessarily a fact.  Please refer to our terms and conditions.

Offline mrchop

  • Jr. Member
  • **
  • Posts: 14
  • Karma: +0/-0
Re: Question 7
« Reply #2 on: May 23, 2010, 04:59:12 PM »
c) State when a sewage pump is required on a foul water drainage system.
  when you can not gravitate it to the conection
(1 mark)
(d)  State where the non-return valve on the outlet of a sewage pump system should be
installed in relation to the isolating valve.
 
(1 mark) depending on the location of pump

on the downstream side of the valve
Total 8 marks
fixing christchurch city one pipe at a time.


Share via digg Share via facebook Share via linkedin Share via twitter

Similar Topics

  Subject / Started by Replies / Views Last post
xx
Question 15

Started by LisaS

0 Replies
2032 Views
Last post February 11, 2009, 08:59:20 AM
by LisaS
xx
Question 14

Started by LisaS

0 Replies
1685 Views
Last post February 11, 2009, 08:59:42 AM
by LisaS
xx
Question 13

Started by LisaS

0 Replies
1726 Views
Last post February 11, 2009, 09:00:14 AM
by LisaS
xx
Question 12

Started by LisaS

0 Replies
1809 Views
Last post February 11, 2009, 09:01:09 AM
by LisaS
 
Share this topic...
In a forum
(BBCode)
In a site/blog
(HTML)